Direct power purchase (DPPA) rulesCơ chế mua bán điện trực tiếp (DPPA)

Amended national rules for buying renewable power directly. Applicability to a given factory is not established.

2/7 · Approved · Phê duyệt chủ trươngLast observed 8 Sep 20262 sources
Readiness ladder · Thang sẵn sàng
Why this stage

Decree 243/2026, issued 26 June 2026, amended Decrees 57/2025 and 58/2025.

Next rung — Investor / contractor selected: A delivery party is selected; construction not yet observed.

Schematic map of Southern Vietnam infrastructure projects by readiness stageApproximate positions of tracked projects in and around Ho Chi Minh City, coloured by observed delivery stage. Not for navigation.ĐỒNG NAITÂY NINHĐỒNG THÁPHỒ CHÍ MINH CITYEast SeaThủ Thiêm–Long Thành Railway — In planHCMC Ring Road 3 — Under constructionHCMC Ring Road 4 — Under constructionMetro Line 2 (Bến Thành–Tham Lương) — Under constructionHCMC–Mộc Bài Expressway — Under constructionHCMC–Thủ Dầu Một–Chơn Thành Expressway — Under constructionBiên Hòa–Vũng Tàu Expressway — Partly operationalBến Lức–Long Thành Expressway — OperationalHCMC–Long Thành–Dầu Giây Expressway (widening) — OperationalMetro Line 1 (Bến Thành–Suối Tiên) — OperationalHCMC coreThủ ĐứcBiên HòaThủ Dầu MộtBàu BàngPhú MỹVũng TàuBến LứcHiệp PhướcCủ ChiLong Thành International Airport (phase 1) — Under constructionCái Mép–Thị Vải deep-water port cluster — Usable for businessCần Giờ International Transshipment Port — Investor / contractor selectedNhơn Trạch 3 & 4 LNG power plants — OperationalHCMC Free Trade Zone (Cái Mép Hạ) — ApprovedVietnam International Financial Centre (HCMC) — OperationalDirect power purchase (DPPA) rules — ApprovedLNG Long Sơn power project — Approved
Observed stage
In plan
Approved
Investor / contractor selected
Under construction
Partly operational
Operational
Usable for business
Site / institution
Schematic, approximate geometry for orientation — not navigation or project alignments. Pole circles follow the structure of the HCMC master plan; they are not official boundaries. Observation run 31 Oct 2026.
Milestones · Mốc kế hoạch và thực tế

Planned against achieved

MilestonePlanned / targetAchievedStatusSource
Amendment issued—26 Jun 2026AchievedElectricity and Renewable Energy Authority
Evidence · Bằng chứng

What the record shows

Unknown · Chưa rõ
  • Effective date of the amended provisions.
  • Tenant eligibility.
  • Whether executable contracts exist at park level.
VIRO analysis

Export manufacturers face buyer pressure on renewable electricity. The test is a signed contract at a specific site.

Serves
Pole 2 · Eastern innovation pole
Pole 4 · Northern industry–logistics pole
Pole 5 · Southern port–FTZ–energy pole
Poles & corridors →
Sources · Nguồn

Next project: Metro Line 2 (Bến Thành–Tham Lương)