Metro Line 2 (Bến Thành–Tham Lương)Tuyến metro số 2 (Bến Thành – Tham Lương)

The second urban-rail line, toward the north-west. Under construction; completion now targeted for Q4 2030.

4/7 · Under construction · Đang thi côngLast observed 31 Oct 20261 sources
Readiness ladder · Thang sẵn sàng
Why this stage

Construction was reported to have started at the Tham Lương depot in January 2026.

Reported  15 Jan 2026 · Pháp Luật TP.HCM

Next rung — Partly operational: Some sections or functions in use; route-wide or full operation not established.

Schematic map of Southern Vietnam infrastructure projects by readiness stageApproximate positions of tracked projects in and around Ho Chi Minh City, coloured by observed delivery stage. Not for navigation.ĐỒNG NAITÂY NINHĐỒNG THÁPHỒ CHÍ MINH CITYEast SeaThủ Thiêm–Long Thành Railway — In planHCMC Ring Road 3 — Under constructionHCMC Ring Road 4 — Under constructionMetro Line 2 (Bến Thành–Tham Lương) — Under constructionHCMC–Mộc Bài Expressway — Under constructionHCMC–Thủ Dầu Một–Chơn Thành Expressway — Under constructionBiên Hòa–Vũng Tàu Expressway — Partly operationalBến Lức–Long Thành Expressway — OperationalHCMC–Long Thành–Dầu Giây Expressway (widening) — OperationalMetro Line 1 (Bến Thành–Suối Tiên) — OperationalHCMC coreThủ ĐứcBiên HòaThủ Dầu MộtBàu BàngPhú MỹVũng TàuBến LứcHiệp PhướcCủ ChiLong Thành International Airport (phase 1) — Under constructionCái Mép–Thị Vải deep-water port cluster — Usable for businessCần Giờ International Transshipment Port — Investor / contractor selectedNhơn Trạch 3 & 4 LNG power plants — OperationalHCMC Free Trade Zone (Cái Mép Hạ) — ApprovedVietnam International Financial Centre (HCMC) — OperationalDirect power purchase (DPPA) rules — ApprovedLNG Long Sơn power project — Approved
Observed stage
In plan
Approved
Investor / contractor selected
Under construction
Partly operational
Operational
Usable for business
Site / institution
Schematic, approximate geometry for orientation — not navigation or project alignments. Pole circles follow the structure of the HCMC master plan; they are not official boundaries. Observation run 31 Oct 2026.
Milestones · Mốc kế hoạch và thực tế

Planned against achieved

MilestonePlanned / targetAchievedStatusSource
Construction start—15 Jan 2026AchievedPháp Luật TP.HCM
CompletionQ4 2030—PendingPháp Luật TP.HCM
Evidence · Bằng chứng

What the record shows

  • Reported
    15 Jan 2026
    The groundbreaking was held on 15 January 2026 at the Tham Lương depot. The adjusted project was approved by the city on 31 December 2025, with completion set for Q4 2030; THACO was selected as main EPC contractor. It is the first city project to use the special mechanisms of Resolution 188. VIRO found no newer progress report.
  • Reported
    15 Jan 2026
    This phase is 11.3 km from Bến Thành along Cách Mạng Tháng Tám and Trường Chinh, ending at Tân Bình station rather than at Tham Lương, which the line is named for.
Unknown · Chưa rõ
  • Current physical progress.
VIRO analysis

Line 2 is the test of whether the network target for 2030 is realistic.