Projects / Airport
Long Thành International Airport (phase 1)Cảng hàng không quốc tế Long Thành (giai đoạn 1)
The eastern air gateway. Equipment testing is under way; the commercial opening is now reported for 24 December 2026, not 1 December.
Readiness ladder · Thang sẵn sàng
Why this stage
The 28 July 2026 official update described the airport as under construction and preparing for trial and commercial operation.
Fact 28 Jul 2026 · Viet Nam Government News
Next rung — Partly operational: Some sections or functions in use; route-wide or full operation not established.
Observed stage
In plan
Approved
Investor / contractor selected
Under construction
Partly operational
Operational
Usable for business
Site / institution
Milestones · Mốc kế hoạch và thực tế
Planned against achieved
| Milestone | Planned / target | Achieved | Status | Source |
|---|---|---|---|---|
| Equipment testing | Sep–Nov 2026 | 29 Sep 2026 | Achieved | Viet Nam News |
| Trials with passengers | Sep–Nov 2026 | — | Unknown | Viet Nam Government News |
| Commercial operation | 1 Dec 2026 → 24 Dec 2026 | — | Slipped | Viet Nam Government News · SGGP English |
Evidence · Bằng chứng
What the record shows
- Target30 Oct 2026Commercial operation is now reported for 00:00 on 24 December 2026, per an ACV notice to the Đồng Nai People’s Committee. Earlier official reporting gave 1 December; sources conflict.
- Target30 Oct 2026The initial schedule is reported at up to 366 flights a week — 322 domestic and 44 international — with Vietnam Airlines and Vietjet named for the first routes. No cargo operator is named.
- Reported1 Oct 2026Testing of escalators, baggage handling, security scanners and runway lights was observed in late September 2026, with a simulated fuel-leak drill; runway lighting was tested on the evening of 29 September. VIRO found no report of trials with passengers.
- Target28 Jul 2026Trial operation was planned for September–November 2026, with commercial operation on 1 December 2026.
- Reported1 Jun 2026ACV reported nearly 76% overall construction progress on 1 June 2026, and 89.55% on the passenger-terminal package.
- Target8 Apr 2025Phase 1 is designed for 25 million passengers and 1.2 million tonnes of cargo a year.
Unknown · Chưa rõ
- Which cargo airlines and ground handlers will operate from day one.
- Scheduled freighter and belly-cargo capacity in the first months.
- Truck transfer times from the main industrial belts once road links open.
VIRO analysis
For electronics and precision manufacturers, an airport only becomes useful when cargo services, customs processing and road access work together. Opening day is a step, not the finish line.
Sources · Nguồn
- Long Thành Airport trial-operation plan — Viet Nam Government News, 28 Jul 2026
- ACV launches 180-day acceleration campaign to deliver Long Thành airport — Airports Corporation of Vietnam, 1 Jun 2026
- Decision 692/QĐ-TTg adjusting the Long Thành International Airport project — Official Gazette of Vietnam, 8 Apr 2025
- Equipment testing under way at Long Thành airport — Viet Nam News, 1 Oct 2026
- Long Thanh airport set to begin commercial operations on December 24 — SGGP English, 30 Oct 2026
Next project: Bến Lức–Long Thành Expressway